On May 21, the Town of Southern Shores announced that the new Trinitie/Juniper Trail bridge is now open to all traffic.

The Town awarded the $1,667,178.70 contract to Smith Rowe, LLC from Mt. Airy, NC on November 4, 2024, with substantial completion of work to take 210 days. The road was closed on December 9, 2024, and the job was completed in 199 days and is expected to come in at or below the contract cost. Kimley-Horn and Associates, Inc., designed and engineered the bridge.

The new core slab bridge replaces a culvert that had been replaced and repaired multiple times. The bridge will become part of the NC Department of Transportation’s bridge inspection program.