OMAHA, Neb. (WOWT) - Organizers with the Omaha Streetcar provided an update on the project for the week of June 2.

Some good news - organizers said the Harney Street Bridge construction related to the streetcar project is ahead of schedule.

Project leaders expect two more closures of I-480 for work on the Harney Bridge, with the first likely to happen after the College World Series ends June 22 or 23, while the second is expected early next month.

Work is almost complete on a temporary lot to help with parking issues in Blackstone related to the project near 40th and Harney Streets. Workers plan to ‘stripe’ the lot later this week, then install city parking equipment.

It is projected to open in about two weeks.