Drivers visiting restaurants, shops, and the Peoria Sports Complex in the P83 Entertainment District should be aware of upcoming street improvement work that will result in restrictions along 83rd Avenue, between the Skunk Creek Wash to Bell Road, over the next two months.

Starting Sunday night, Aug. 24, Peoria streets crews and its contractors will start removing existing asphalt in the area, preparing for asphalt pavement overlay that will be scheduled for late September.

Asphalt removal and repaving prep: Aug. 24-29 | 8 p.m.-11 a.m.

Crack repair: Beginning Sept. 3 | 3-11 a.m.

Paving work: Beginning Sept. 28 | 8 p.m.-11 a.m

Stamped concrete work: Beginning Oct. 15 | 3-11 a.m.

Traffic Impacts:

• At least one lane in each direction will remain open during work

• Left turns may