HOLLY RIDGE, La. -- In a rural corner of Louisiana, Meta is building one of the world's largest data centers, a $10 billion behemoth as big as 70 football fields that will consume more power in a day than the entire city of New Orleans at the peak of summer. While the colossal project is impossible to miss in Richland Parish, a farming community of 20,000 residents, not everything is visible, including how much the social media giant will pay toward the more than $3 billion in new electricity infrastructure needed to power the facility. Watchdogs have warned that in the rush to capitalize on the AI-driven data center boom , some states are allowing massive tech companies to direct expensive infrastructure projects with limited oversight. Mississippi lawmakers allowed Amazon to bypass regul
Louisiana's $3B power upgrade for Meta project raises questions about who should pay