MONTOURSVILLE — It will cost nearly $200 million to complete the major work on a thruway project in central Pennsylvania, based on the bids opened Thursday by the Pennsylvania Department of Transportation.

The low bid of $186,381,639 to pave and do other assorted work on the southern section of the Central Susquehanna Valley Thruway (CSVT) was submitted as a joint venture by two Allegheny County firms, Trumbull Corp. and Golden Triangle Construction Co.

The bid is approximately $1.3 million lower than the one submitted by New Enterprise Stone Lime Co. of Bedford County. Two others were also received.

“We are looking forward to starting the last contract for this long-awaited project,” said Eric High, PennDOT district executive.

“The new highway will not only improve safety by separatin