The Oregon Public Utility Commission has reaffirmed its approval of a nearly 300-mile electrical transmission line that’s set to run from Idaho and carry power across five Oregon counties – despite concerns it will primarily serve a private data center rather than the public.
The commission on Thursday declined to rescind a certificate that authorizes Idaho Power, the developer and co-owner of the Boardman-to-Hemingway project – B2H for short – to seize private land via eminent domain. Regulators maintained the line remains in the public interest.
The decision came in response to a petition filed this summer by the nonprofit Stop B2H Coalition and its co-chair, Irene Gilbert, a retired government employee who has challenged the project for years over its impact on Oregon’s rural land