Learn more about transportation projects in the McKinney area that are currently underway. Projects listed are underway with completion expected to come in 2026, according to McKinney's Capital Improvement Program . This list is not comprehensive.
1. SH 5 utility relocations
Project: Relocation of existing water and wastewater mains ahead of planned SH 5 reconstruction project by the Texas Department of Transportation.
Update: The contractor has substantially completed all utility relocations south of Eldorado Parkway. Construction will continue to progress north through the downtown area.
Timeline: mid 2024-late 2026
Cost: $31.4 million
Funding source: city of McKinney, TxDOT
2. Virginia Parkway and Eldorado Parkway street rehabilitation
Project: Reconstruction of failing