Learn more about transportation projects in the McKinney area that are currently underway. Projects listed are underway with completion expected to come in 2026, according to McKinney's Capital Improvement Program . This list is not comprehensive.

1. SH 5 utility relocations

Project: Relocation of existing water and wastewater mains ahead of planned SH 5 reconstruction project by the Texas Department of Transportation.

Update: The contractor has substantially completed all utility relocations south of Eldorado Parkway. Construction will continue to progress north through the downtown area.

Timeline: mid 2024-late 2026

Cost: $31.4 million

Funding source: city of McKinney, TxDOT

2. Virginia Parkway and Eldorado Parkway street rehabilitation

Project: Reconstruction of failing