KPI Green Energy Ltd has received a work order worth ₹489.17 crore from Gujarat State Electricity Corporation Ltd (GSECL) to execute a 142 MW (DC) / 110 MW (AC) floating solar project at the Kadana Dam reservoir in Gujarat.
The EPC contract covers complete design, engineering, procurement, construction and installation of the floating PV system, alongside grid-connection works that include a 33 kV underground transmission line to the pooling station and 33/220 kV bays at the Kadana substation.
The project, which will be executed over 18 months, also includes a 10-year operations and maintenance component. KPI Green said the contract strengthens its position across ground-mounted, rooftop and now floating solar segments.
Dr Faruk G Patel, Chairman and Managing Director, KP Group, said t

CNBC-TV18

Businessline
The Economy Times Markets
Providence Journal Sports
AlterNet
New York Post
America News
The Manchester Evening News Crime
CNN Business
The Babylon Bee