FAIRMONT, W.Va. (WBOY) — All six lanes of Interstate 79 in Marion County are finally open after a more than four-year widening project.

Cones were removed from the construction zone Thursday morning, marking the completion of the expansion of I-79 from four lanes to six between mile markers 132 and 135 between White Hall and Fairmont.

The project began back in May 2021 and was originally scheduled to be completed in September 2024, although a project update in 2024 pushed that date back to summer of 2025.

The West Virginia Department of Transportation took home an award for the $72.5 million widening project earlier this month. The America’s Transportation Award for Best Use of Technology and Innovation was given for the replacement of the twin South Fairmont bridges on the interstate t