Construction on the 65-turbine Revolution Wind project off the coast of Martha’s Vineyard can resume after a federal district court judge granted the developers reprieve from a stop work order issued by the Trump administration.

In a ruling on Monday, D.C. district court Judge Royce Lamberth granted Revolution Wind a preliminary injunction, halting the enforcement of an Aug. 22 order from the Bureau of Ocean Energy Management , or BOEM.

“Revolution Wind has demonstrated likelihood of success on the merits of its underlying claims, it is likely to suffer irreparable harm in the absence of an injunction, the balance of the equities is in its favor, and maintaining the status quo by granting the injunction is in the public interest,” the judge wrote in his two-page opinion.

When the Trum