In a major milestone, the 624 megawatt Kiru hydroelectric project, under construction on the Chenab River in the Kishtwar district of Jammu and Kashmir, has reached a significant milestone with the completion of 10 lakh cubic meters of Dam Concreting, out of a total target of 12 lakh cubic meters.
This achievement marks a critical step towards the full realization of the dam structure, bringing the project closer to completion, the Chenab Valley Power Projects Ltd (CVPPL) announced on Saturday.
Advertisement
In another key development, the Stator Assembly of Unit-1 has commenced in the power house, giving further boost to the pace of power house completion in line with the project timeline.
On this occasion, MD CVPPL congratulated the entire Kiru Project team for their dedication and h