VICTORIA — B.C. Hydro completed 40 years worth of state-of-the-art studies into the geotechnical risks at Site C before the start of construction in 2015.
But the government-owned utility discounted the findings as “low risk” albeit with “high consequences” if they materialized.
Nor did Hydro make provisions in the budget to cover the cost of those “high consequences” if the risk estimation was proven wrong.
Advertisement
Advertisement
Advertisement
Advertisement
Alas for Hydro ratepayers, the risks did materialize in the form of tension cracks on the north bank of the Peace River in 2017 and growing displacements in 2018 under the right bank foundations for the dam, spillways and generating station.
The fixes blew huge holes in the budget, delayed construction by a year and raised

Yahoo Canada

The List
FOX19 NOW
FOX19 NOW Sports
AlterNet
The Daily Beast
FOX 10 Phoenix National
CNN
The Columbian Politics