A project outside of Selma's Retama Park is now complete, while other projects are currently ongoing across the Northeast San Antonio Metrocom.

Completed projects

Retama Parkway Reconstruction

Project: Construction added approximately 4,500 linear feet of roadway with 6-foot sidewalks and bike lanes along Retama Parkway. The project also included right-of-way improvements to portions of Alton Boulevard.

Update: The project was completed Nov. 4, reopening the intersection of Retama Parkway and Lookout Road.

Timeline: October 2024-November 2025

Cost: $5.31 million

Funding source: city sales tax

Ongoing projects

FY25 Street Rehabilitation Package II

Project: The project will reconstruct Firebird Run, Silver Wing and Town Creek Road in Cibolo.

Update: According to the c

See Full Page