A project outside of Selma's Retama Park is now complete, while other projects are currently ongoing across the Northeast San Antonio Metrocom.
Completed projects
Retama Parkway Reconstruction
Project: Construction added approximately 4,500 linear feet of roadway with 6-foot sidewalks and bike lanes along Retama Parkway. The project also included right-of-way improvements to portions of Alton Boulevard.
Update: The project was completed Nov. 4, reopening the intersection of Retama Parkway and Lookout Road.
Timeline: October 2024-November 2025
Cost: $5.31 million
Funding source: city sales tax
Ongoing projects
FY25 Street Rehabilitation Package II
Project: The project will reconstruct Firebird Run, Silver Wing and Town Creek Road in Cibolo.
Update: According to the c