On Monday, crews are scheduled to begin what is expected to be a yearlong project to repave 19th Avenue through San Francisco's Sunset District, one of the city's busiest roadways.
According to Caltrans , the first phase of construction will repave the roadway beginning at Sloat Boulevard, continuing north towards Lincoln Way next to Golden Gate Park. Officials said parking strip repaving will be completed before full lane repaving begins.
Crews prepare for paving work along 19th Avenue near Sloat Boulevard in San Francisco, Dec. 1, 2025. CBS
The second phase of construction involves full lane repaving from Holloway Avenue to Lincoln Way, which is set to begin in spring of 2026. In June, repaving the southbound lanes of 19th Avenue from Sloat Boulevard to Holloway is set to take plac