Kalaburagi (Karnataka) [India], December 5 (ANI): The Solapur Division of Central Railway has achieved a major milestone under the Indian Railways' ambitious scheme of 1x25 kV to 2x25 kV Auto Transformer (AT) feeding system upgradation project being implemented on the Golden Quadrilateral route between Mumbai and Chennai to facilitate the Government's Mission 3000 MT, according to an official release issued by the Public Relations Department, Solapur Division, Central Railway.
As part of the ongoing modernisation works in the Solapur-Wadi section, the Division successfully completed the track crossing operation, thus commencing the commissioning process for the 1st Scott Transformer received in Central Railway for the upcoming Gaudgaon Traction Sub Station (TSS).
The Gaudgaon TSS is situ