New Delhi, Dec 8 (PTI) Central Transmission Utility of India Ltd (CTUIL) has revoked connectivity of 24 entities, having renewable energy (RE) capacity of 6,343 MW, since 2022, the power ministry said on Monday.

The cancellations of the grid access permission are on account of delays from the developers' end and not due to transmission side delays.

"Since 2022, Central Transmission Utility of India Limited (CTUIL) has revoked connectivity of 24 grantees with a Renewable Energy (RE) capacity of 6343 MW, " a ministry statement said, adding that the information was shared by the Minister of State for Power, Shripad Yesso Naik, in a written reply in the Rajya Sabha.

There are sixteen petitions pending before the Central Electricity Regulatory Commission that pertain to cases where the petit