Reconstruction of the pavement on LaSalle Road is scheduled to begin Sept. 15.
Phase 3B of the West Hartford Center Infrastructure Master Plan underway on the west side of LaSalle Road. Sept. 8, 2025. Photo credit: Ronni Newton
By Ronni Newton
Implementation of the West Hartford Center Infrastructure Master Plan on LaSalle Road – which has been underway since the spring – is continuing to progress through the phases as scheduled, but officials announced last week that more extensive reconstruction of the roadway will be required.
“Originally, a simple mill and overlay was planned for LaSalle Road. Unfortunately, there were unforeseen issues during construction, which resulted in this scope change,” the construction management team from M&J Engineers stated in a news release last week.