CALUMET – The ongoing project at the Calumet Theatre to restore steam heat to the theater promises a warm space for shows and events this winter.

In Sept. 2024 a new boiler was ordered to replace an existing one that had failed. Installation of the new boiler was completed by Marty’s Heating Services, of Hancock, in January, with Phase One of the project completed by March of this year. This included removing the old, failed boiler, installing the new unit, and having it inspected and licensed. Along with the failed boiler, old manifolds were removed and new, threaded, manifolds were restored, replacing the old, welded ones.

Phase Two included repairing, fitting, packing, and testing steam pipes throughout the building.

Calumet Theatre Co. President Dan Jamison said Marty Trevathan of M