HINTON, Iowa (KCAU) — There is a significant update regarding the Highway 75 construction project from Hinton to Merrill.

According to the Iowa Department of Transportation, contractors have completed the culvert extensions and are currently working on grading the road. Once the grading is finished, the next step will be concrete paving, scheduled to begin on September 26.

Story continues below • Top Story: Conservative Charlie Kirk dead after being shot during Utah event • Lights & Sirens: Sioux County crash kills teen, injures another • Sports: Local high school volleyball highlights and scores (9-9-25) • Weather: Get the latest weather forecast here

While the ongoing construction may cause some traffic delays, Iowa DOT officials emphasize the importance of patience among driv