Oracle began delivering Nvidia GB200 racks in June 2025, enabling the site to begin running early AI training and inference workloads
In sum – what to know:
Abilene AI hub goes live – Crusoe has powered the first phase of its flagship Texas campus, developed with Oracle, marking a major milestone in U.S. AI infrastructure buildout.
Rapid construction – Two buildings went live within a year of groundbreaking, already running Nvidia GB200 racks to support AI training and inference workloads.
Blueprint for AI – The planned eight-building campus will host hundreds of thousands of GPUs on one network fabric, blending liquid and air cooling for high-density operations.
AI infra company Crusoe has officially powered up the first phase of its flagship Stargate data center campus in Abile