Learn more about transportation projects in the McKinney area aimed at improving utilities and roadways. Projects listed are either underway or expected to start within the next year. This list is not comprehensive.

Ongoing projects

1. SH 5 utility relocations

Project: Existing water and wastewater mains are being relocated ahead of the planned SH 5 reconstruction project by the Texas Department of Transportation.

Update: Construction on the first phase is underway.

Timeline: mid 2024-May 2026

Cost: $31.4 million

Funding source: city of McKinney, TxDOT

2. Virginia Parkway and Eldorado Parkway street rehabilitation

Project: Reconstruction of failing concrete panels and broken curbs along Eldorado Parkway between Ridge Road and US 75, and Virginia Parkway between Stonebridge D