Read about some of the latest updates on road and capital projects around League City. This list is not comprehensive.

Upcoming projects

Clear Creek Avenue asphalt rehab

Project: will include reconstruction of the road from E. Walker Street to E. Galveston Street.

Update: Funding to come in 2026.

Timeline: contract for construction awarded in October with work to start in January

Cost: $365,013

Funding source: funded through a community development block grant and city cash as needed

North Landing Boulevard extension

Project: includes construction of around 1.7 miles of four-lane road with two bridges and a boulevard to divide road

Update: Design for the project has been completed but work remains a couple years away

Timeline: Texas Department of Transportation pushed bi