According to the minister, only 4,148 ROB/RUBs were constructed between 2004 and 2014.
The construction work of ROB in lieu of LC No. 43/Spl/E at KM 239/9-10 in Azimganj- New Farakka section of Malda Division has been sanctioned. The work for the preparation of the General Arrangement Drawing (GAD) and Detailed Estimate has been taken up, the minister told the Lok Sabha.
Out of 302 sanctioned ROB/RUB works in West Bengal, 99 Nos. ROB/RUB works are delayed on account of the State Government.
According to the Railway Minister, 41 works in West Bengal are in finalization of Alignment; 14 are delayed due to General Arrangement Drawing stage; 27 for NOC for closure of LC; 10 due to land acquisition; 7 due to Law and order or public protest, amounting to 99 works left pending.