A traffic study conducted in 2023 will lead to improvements in traffic signals and pedestrian crossing at SH 114 and Championship Parkway, near the Texas Motor Speedway.
The estimated project is $5 million, with Denton County funding $3.5 million of it. The city of Fort Worth will use $1.5 million from Tax Increment Reinvestment Zone No. 2 to pay for design and construction. Denton County will advertise, bid and award the contract for the work, according to city documents.
According to city documents , work will start Jan. 31, 2026, and will be completed no later than Jan. 1, 2028. There is a six-month option for an extension, if needed.
A closer look
According to city documents, pedestrian crossings will be added due to safety concerns for northbound and southbound traffic near th