Nearly 50 additional large, concrete beams will be delivered and set in November for another bridge that is part of Section 3 of the I-69 Ohio River Crossing (ORX) between Henderson and Evansville, Ind., the approach work in Evansville.

The 48 concrete beams range in length from 134 feet to 163 feet long. Four beams are expected to be delivered each day, with one beam transported per truck. Beam delivery and setting is scheduled to begin Monday, Nov. 3 and continue through Friday, Nov. 21.

Daily deliveries are expected each week, Monday through Thursday. As beams are delivered, two short-term rolling closures lasting about five to 10 minutes each are expected on U.S. 41 in Indiana, to allow delivery vehicles to safely make the left turn from southbound U.S. 41 to Waterworks Road (which i