Forty-eight additional large, concrete beams will be delivered next month for another bridge that is part of the I-69 Ohio River Crossing.

The beams range in length from 134 feet to 163 feet.

Four beams are expected to be delivered each day, with one beam transported per truck.

That work is expected to begin Monday, November 3, and continue through Friday, November 21.

Ohio River Crossing Section 3 is expected to be 60 percent complete by the end of this year and is on schedule to be completed by late 2026.