Work on US-191 in Indian Canyon continues. Crews this fall have been working at multiple locations. The areas of focus have been or will be: Milepost 267-269 where crews are removing dirt to build six foot wide shoulders on each side of the road; Milepost 272-275 where crews are building the foundation for passing lane and chain-up/off areas. They have removed the paved shoulder of the road and are filling in the road base for a new passing lane and chain-up/chain-off areas; Milepost 285 and Right Fork Canyon Road where crews are preparing to widen the road shoulders near Right Fork Canyon Road to allow for easier turning; Milepost 291 and Skitzy Canyon Road where crews are preparing to widen the road shoulders near Skitzy Canyon Road to allow for easier turning; and Milepost 292 and Sower

See Full Page